Info

Before reading this page, it is highly recommended you read the Time Trigger page.

 

Monthly The monthly trigger will start a build once a month at a specified time.

Image Added

Image Removed

You can manually enter a time or use the time picker to insert one (you can use short cuts to change the time, the Time Triggers page explains them). Once a time is selected, you then choose which day it executes on by selecting On day number from the Repeat drop down then typing in a day number. Alternatively you can select a week option from the Repeat drop down, for example, First, Second, Third, Fourth or Last week of the month then specify the day of that week.

Time

The time when a build should be fired. Note that this property uses 24 hour format.

Repeat

Specifies which day of the month will fire a build. This field can be one of the following values:

  • On day number: A build will be triggered on a specific day number. If this value is selected then the Day Number property must also be set.
  • On the first: A build will be triggered on the first week of each month on a specific day. If this value is selected then the Day property must also be set.
  • On the second:  A build will be triggered on the second week of each month on a specific day. If this value is selected then the Day property must also be set.
  • On the third:  A build will be triggered on the third week of each month on a specific day. If this value is selected then the Day property must also be set.
  • On the fourth:  A build will be triggered on the fourth week of each month on a specific day. If this value is selected then the Day property must also be set.
  • On the last:  A build will be triggered on the last week of each month on a specific day. If this value is selected then the Day property must also be set.

Day Number

Image Added

This property can only be set if Repeat is set to On day Number. This property sets the day of the month that a build should be triggered.

Note that if a month does not include a day number then a build will be executed on the last day of the month instead. For example, if your trigger fires a build on the 31st of every month, any months that have 30 days will instead trigger a build on the 30th.

Day

Image Added

This property specifies the day that a build should be triggered. Note that this property is only available when Repeat is not set to On day number.

In the above example, a build will be executed on the first Sunday of every month.